论文首先分析了我国进出关铁路通道的布局、各进出关口的功能及现状运量,然后根据对历史数据和未来发展形势的分析,在获得全国铁路进出关客货运量水平的基础上,对通道各个关口进行分工,得出京唐通道客货运总量预测结果,再将需求预测结果与线网能力进行能力适应分析。经过计算,京哈线北京至唐山段2020年能力利用率为96.8%,已基本饱和;2025年能力利用率为113.9%,能力不足,故2025年前京哈线北京唐山间需要修建新线;通过对替代方案分析,结合京津冀地区土地开发前景,确定结合修建北京枢纽东南环线新建京唐城际的建设方案。
Abstract:This paper first introduced the layout of the railway passages at the inlet and outlet pass,and its function and capacity.Then,by analyzing the historical data and growing trend,the national railway passenger and freight volume into the passage were forecasted.On the basis of this,the volume into the inlet and outlet pass was calculated and the division was made.After that,the railway passenger and freight volume through Beijing-Tangshan corridor were forecasted.Finally,the demand and railway capacity were contrasted to determine the right construction timing.The results indicated that,in 2020,the capacity utilization rate of Beijing-Tangshan section of Beijing-Haerbin rail would be 96.8%,which is almost saturated,and in 2025 the capacity utilization rate would be 113.9%,which means lack of capacity.So,new lines should be constructed between Beijing and Tangshan before 2025.After analyzing the alternative schemes and the perspective of land development in Beijing-Tianjin-Hebei area,the construction scheme of Beijing-Tangshan intercity railway was determined combining with the construction of the southeast circle line of Beijing railway hub.
[1]刘万明.高速铁路最佳建设时机研究[J].数量经济技术经济研究,2002,(8):29-32.
[2]闵国水.皖赣铁路扩能改造的必要性及建设时机研究[J].铁道运输与经济,2011,33(9):14-27.
[3]张国宝,张国栋.京沪高速铁路技术模式及修建时机探讨[J].铁道运输与经济,2001,(1023):34-36.
[4]李云耀.建龙铁路建设必要性时机及主要技术标准研究[J].交通科技,2008,(S1):104-107.
[5]新建铁路北京至秦皇岛城际铁路北京至唐山段建设时机研究报告[R].天津:铁道第三勘察设计集团有限公司,2011.
[6]姜新华.正确运用客货运量预测方法为铁路发展提供决策支持[J].铁道运输与经济,2005,27(5):30-32.
[7]陈嘉.珠三角城际轨道交通穗莞深线项目建设问题探讨[D].南昌:华南理工大学,2008.
[8]王彬.南昌借鉴香港地铁经验建设城市轨道交通初探[D].南昌:南昌大学,2011.
基本信息:
DOI:
中图分类号:U239.5
引用信息:
[1]曾鸣凯.北京至唐山城际铁路建设时机研究[J],2012,10(02):19-26.
基金信息: